FINLAND — IMPLEMENTATION OF ON-SITE MOBILE PROCESSING AND DELIVERY OF ELEMENTS

In September, the WWTECH Engineers faced a demanding project on the implementation of on-site mobile machining and delivery of components that were previously dismantled and sent to us.

The elements we had to process had to be processed on our tool shop. After this process was completed, they were subjected to NDT tests.

After arriving at the workplace, the gentlemen began on-site mobile processing (cleaning diffusers, polishing diffusers with unloading sleeves). Next, the spindles were mounted and the sleeve – diffuser – was manually lapped.

The given task was subjected to final tests, the result of which was positively assessed by the Employer.